Nordic's Power Demands & CMP Expansion

Line 80 Rebuild for Nordic's Power Demand.

The rebuilt line will be 80 feet high. The distance from the rebuilt line to the edge of the ROW would increase to 105 feet. The line runs from Coopers Mills in Windsor to Highland substation in Warren.

Click Below Links for More Details on Expansion 

"For the reasons described herein, the Public Utilities Commission (PUC or Commission) should deny the request of Central Maine Power Company (CMP) for a Certificate of Public Need and Convenience (CPCN) for its Section 80 Rebuild Project on the grounds that the request is premature and that CMP has failed to adequately demonstrate the asserted need. In its filing and subsequent updates, CMP has failed to document that the proposed capacity upgrade is necessary to meet the needs of the Midcoast region."